Reduced Footprint on Harbor Island – Project Scope Change

By September 9, 2020 December 10th, 2020 No Comments

We have informed MARAD of a project design update regarding the proposed facility plans for Harbor Island.  We have reduced our footprint on Harbor Island by relocating pumps and storage tanks to our planned onshore Multi-Use Terminal near Taft.  The revised design still maintains pipeline flushing capabilities to ensure safe and responsible operations.  Harbor Island remains an important facility location for BWTX project components including a building for personnel; industrial equipment for inspection, monitoring and communications;  a storm surge levee; and an access road.  MARAD is seeking public comment via the Federal Register.